Modular Childcare Unit Extension at Cwrt Rawlin Primary School

The Project

Elite Systems was commissioned to design and manufacture a modular childcare unit for Cwrt Rawlin Primary School, located in Cae Meillion, Caerphilly, South Wales.

This project was part of the school’s ongoing efforts to enhance its facilities and expand its teaching space. The modular extension not only provided much-needed room for childcare services but also seamlessly integrated with the school’s existing sports hall, improving the learning environment for both students and staff.

Thanks to our bespoke approach, we were able to design the modular building with four precisely sized units—two measuring 12m x 2.5m and two at 10.3m x 3.6m. 

 

CCS Supplier, Considerate Constructors, Investors in People, ISO

 

 

Features & Benefits

General superstructure

A single storey steel frame building with 25-year structural warranty.

External walls

Plastisol & timber clad, providing a sleek, modern, and contemporary aesthetic while ensuring low maintenance.

Roof

Warm deck roof, EPDM roof cover, also comes with a 25-year warranty, guaranteeing long-term reliability and peace of mind.

Ceiling finish

600 x 600 tiles in white t-section grid with black shadow batten, provides a modern, clean look with improved acoustics, better lighting reflection, and easy maintenance access.

Internal walls

Foil backed plasterboard, double boarded and fully decorated in the client’s chosen colour, ensuring a high-quality, personalised finish.

Floor coverings

Vinyl wood comfort and entrance matt to lobby, offering the look and feel of wood while offering enhanced comfort underfoot and noise reduction.

Low-Level Sinks

Designed for accessibility and ease of use, these sinks promote independence for children and individuals with limited mobility.

Tiled Splashback to Kitchen Area

Provides a durable, water-resistant surface that is easy to clean. This feature replicates the style and functionality of a traditional build, offering both practicality and aesthetic appeal.

Permanent Fencing Around the Building

Ensures long-term security and safety for both the school and the building.

 
 
  

The challenge...
...and how we approached it

The Biggest Challenge
  • Adapting to the school’s sloped landscape.
  • Installing secure piers at the front of the building while maintaining level access at the rear.
  • Rerouting existing drainage systems to accommodate the new structure.
Working Within a Live School Environment
  • Prioritising safety at every stage to ensure minimal disruption to students and staff.
  • Installing secure Heras fencing to maintain a safe worksite.
  • Modular units delivered and installed over a weekend to reduce interference with school activities.
  • Implementing stringent measures to minimise disruption during school hours.
Approach to Sloping Terrain
  • Installing pad foundations at varying levels to provide a stable and secure base for the modular unit.
  • Constructing blockwork piers for additional structural support.
Drainage System Adjustments
  • Carefully rerouting existing drainage systems around the building’s footprint.
  • Making significant depth adjustments to align with live public sewer connections.
Safety Measures
  • Establishing exclusion zones and secure fencing to ensure safety.
  • Careful planning and scheduling to avoid peak school hours for potential disruptions.
Communication with the School
  • Strong communication with the school to ensure all parties were informed and operations ran smoothly.
  • Ensuring smooth operation during weekend work to avoid disruption to the school environment.
Back to top

“Delivering this childcare unit for Cwrt Rawlin Primary School was a rewarding challenge. Despite the site’s sloping terrain, we were able to design a solution that seamlessly integrated with the school’s existing infrastructure, all while ensuring minimal disruption. It’s great to see the positive impact this space has already had on the school, and we’re proud to have contributed to their growth.”

— Marcus Sutcliffe, Director at Elite Systems GB

Copy-of-20240408_Nozzle_Headshot-1

 

The Results

We successfully delivered a state-of-the-art modular childcare unit, providing Cwrt Rawlin Primary School with essential additional space for childcare services and teaching. The modular unit was integrated seamlessly into the existing school infrastructure, with careful planning ensuring minimal disruption to the daily school environment.

 Elite Systems’ expertise in modular construction led to the completion of the project within budget and on schedule. The high-quality materials, bespoke design, and efficient construction process resulted in a cost-effective and sustainable solution. The new extension has not only expanded the school’s capacity but also enhanced the overall educational experience for students, providing a flexible space that can adapt to the school’s future needs. 

This project stands as an example of Elite Systems’ commitment to delivering practical, high-performance modular buildings that meet the unique requirements of educational institutions.

 

For an informal chat
about your project

No Comments Yet

Let us know what you think